S Korea’s Polymirae shuts two Yeosu PP lines

陈燕

  • 2

    留言
  • 596

    浏览
South Korea’s Polymirae shut its No 1 and 2 PP lines in Yeosu late Tuesday due to problems in their process control systems. The 150,000 tonne/year No 2 line was expected to resume production on Thursday and would run at 80% of capacity for the rest of the year due to mechanical issues, while the No 1 line with the same capacity was due to restart on 20 November. The producer would gradually ramp up output at the No 1 line to 100% and the production losses from the outage were estimated at 2,000-3,000 tonnes. Polymirae’s 170,000 tonne/year No 3 PP line was restarted on 15 November after it was shut for eight days due to a power failure, and was estimated to have lost 5,000 tonnes of output.
2009-11-18 收起回复

陈燕: 它的年产17万的3号装置已于15号重启,估计损失5,000吨产量。 1号装置预计损失2,000-3,000吨。

2009-11-18

陈燕: 由于生产控制系统出现了毛病,韩国Polymirae于昨天停车了其丽水的1号和2号聚丙烯装置。其中,年产15万的2号装置 有望星期四恢复生产,开工率预计为80%,年产同样为15万的1号装置预计11月20号重启。

2009-11-18

总条数:2条